Stage 03 · Connection Strategy

Most rejections start with the wrong route.

We check the site, the equipment and the export you need, then confirm G98, G99 or G100 before anything reaches the DNO.

Free advice · Every DNO · Domestic to utility scale

The routes

Four routes. One is right for your project.

It comes down to inverter rating per phase, total generation on site and how much you need to export.

Connect & notify

G98

Small inverter systems up to 16A per phase. Installed first, then notified to the DNO within 28 days.

G98 notifications
Apply before install

G99

Anything over 16A per phase, or multiple G98 units on one site. Needs DNO approval before installation.

Formal application
Export limitation

G100

Where the network can't take full export, a G100 compliant export limitation scheme keeps the project viable.

Battery & G100
Larger schemes

Full connection application

Commercial and utility scale projects that need a formal connection offer and possibly reinforcement.

Commercial & utility

How we decide

What we check before recommending a route

  1. 01

    Existing supply

    Phase, cut-out rating, MPAN and anything already generating on site.

  2. 02

    Proposed equipment

    Inverter ratings per phase, battery, EV and heat pump loads.

  3. 03

    Export required

    Whether full export is realistic or a G100 limit is the better option.

  4. 04

    Recommended route

    A clear recommendation so the formal application goes in right first time.

Pricing

Strategy advice is free

Connection strategy is advisory and costs nothing. You only pay once we prepare and submit the formal application, priced by system size.

G99 application fee by system size

4 – <50 kW

£125 + VAT

Large domestic solar, e.g. 8–12 kW

50 – <500 kW

£225 + VAT

Commercial rooftop, small industrial

500 kW – <1 MW

£545 + VAT

Ground mount, large commercial

Over 1 MW

POA

Solar farms and large scale

  • Route recommendation (G98 / G99 / G100)
  • Export limitation advice
  • Existing equipment review
  • No obligation

DNO fees are not included

Some DNOs charge their own assessment or connection fees. These are separate from our fee and we'll tell you where they apply.

Before we start

What we need from you

  • MPAN and supply phase
  • Photo of the cut-out
  • Details of any existing generation
  • Proposed equipment and kW

The final decision on the route always sits with the DNO. We make sure what they receive points to the right one.

FAQs

Connection strategy FAQs

Get the route right before you submit.

Tell us about the site and the system. We'll confirm the right route and take it from there.