When should I request feasibility rather than a G99 application?

How to choose between a feasibility study and a straight G99 application.

Written by the DNO Renewables teamUpdated

Both routes give you a formal DNO position on the project. The question is at what cost and at what point in the project lifecycle.

Choose feasibility first when

  • Project size is significant (typically above ~500 kW, always above ~1 MW).
  • You're not yet committed to spending on a full application.
  • Customer is evaluating multiple sites.
  • You suspect the local network might be constrained.
  • You want an indicative cost before scoping investment.

Go straight to G99 when

  • Project is small to mid-scale and within Fast Track thresholds.
  • Site is in an area you know is unconstrained.
  • Customer is committed to proceeding at this site regardless.
  • Timeline is tight and the G99 route is faster than sequential feasibility then application.

What feasibility doesn't do

Feasibility gives you an indicative view of the network, not a formal connection offer. If the project is definitely going ahead, you'll still need a full application afterwards — the feasibility work informs it but doesn't replace it.