The five stages

One team, from site assessment to energisation.

Every project is different. You may need support at one stage or throughout the journey. Our team helps you identify the right starting point and manage the DNO requirements as your project progresses.

  1. 01

    01 – Grid Feasibility

    Understand the network before committing.

    Assess the potential for connecting your project to the local electricity network before progressing with detailed design or significant investment.

    What we do

    • Identify the relevant DNO
    • Review proposed import and export requirements
    • Coordinate feasibility or budget estimate enquiries
    • Review indicative network constraints
    • Explain the findings and possible next steps
    Outcome: An initial understanding of potential connection capacity, constraints and indicative costs, subject to the DNO's assessment.
    Explore Grid Feasibility
  2. 02

    02 – Connection Strategy

    Choose the appropriate application route.

    Determine the most suitable connection approach based on your project, proposed equipment, capacity requirements and existing supply.

    What we do

    • Review project requirements
    • Identify the relevant application route
    • Consider G98, G99 and other applicable processes
    • Review import and export arrangements
    • Identify potential G100 requirements
    • Advise on the information needed for submission
    Outcome: A clearer application route and understanding of the documentation and technical information required.
    Explore Connection Strategy
  3. 03

    03 – Formal Application

    Prepare and submit to the DNO.

    We prepare and submit the agreed application to the relevant network operator, checking the information and supporting documents before submission.

    What we do

    • Review project information
    • Prepare the applicable DNO forms
    • Coordinate supporting technical documents
    • Check the information for consistency
    • Submit to the relevant DNO
    • Obtain and record the application reference
    Outcome: An application submitted to the appropriate network operator, with the reference and available documents recorded in your project portal.
    Explore Formal Applications
  4. 04

    04 – DNO Management

    Queries handled. Progress chased.

    Submission is only the beginning. We manage DNO correspondence, coordinate responses to technical queries and proactively follow up throughout the assessment.

    What we do

    • Monitor application progress
    • Handle DNO correspondence
    • Coordinate technical queries
    • Chase outstanding responses
    • Keep project information organised
    • Share DNO decisions and connection offers
    Outcome: An organised, actively managed application with progress updates and correspondence available through your portal.
    Explore DNO Management
  5. 05

    05 – Commissioning

    Complete the post-installation requirements.

    Following installation, we can help coordinate and submit the applicable DNO commissioning and post-installation documentation.

    What we do

    • Identify the relevant DNO commissioning requirements
    • Prepare or coordinate applicable forms
    • Review information supplied by the installer
    • Submit required documentation to the DNO
    • Manage follow-up queries
    • Record available confirmation documents
    Outcome: Applicable DNO commissioning submissions completed and tracked, subject to the information, testing and certification supplied by the responsible installer or engineer.
    Explore Commissioning
Who does what

You, DNO Renewables and the network operator.

Grid connection projects involve several parties. Here's how responsibilities are typically divided when you use our managed application service.

StageYouDNO RenewablesNetwork Operator
Supply project informationPrimaryReview—
Provide technical designs and equipment dataResponsible specialistCoordinate and review for applicationAssess where required
Application preparationProvide inputsLead—
Application submissionAuthoriseLeadReceive
Network assessment—LiaiseLead
Technical queriesSpecialist answers where neededCoordinate and manageRaise and assess
Application progress chasing—LeadRespond
Connection offer / decisionReview and decideExplain and coordinateIssue
Offer acceptanceAuthorise and acceptSupport where agreedProcess
Physical electrical installationAppointed contractor—Network works where applicable
Commissioning testing and certificationResponsible installer / engineerCoordinate documentationWitness / assess where required
Commissioning submissionProvide recordsSubmit where includedReview / acknowledge

Responsibilities vary by project, application type and agreed service scope.

Two ways to work

Manage it yourself when you want to. Hand it to us when you don't.

Use our platform to organise your own applications, or let our specialist team handle the DNO process for you. Both options keep your projects in one place.

Free CRM

Manage It Yourself

Use our free installer portal to organise and track your own DNO applications, documents and correspondence.

  • • Keep your projects in one place
  • • Store application documents
  • • Record DNO references and milestones
  • • Maintain project notes and correspondence
  • • Request managed support when needed
  • • Free to use for installers
Explore the Free CRM

Managed service

Let Us Manage It

Our UK-based team prepares and manages your DNO applications, handles correspondence and proactively follows up on progress.

  • • Specialist application review
  • • Application preparation and submission
  • • DNO technical query coordination
  • • Proactive progress chasing
  • • Portal updates and document management
  • • Commissioning support where included
Explore Managed Services
Everything in one place

Track every stage on the project page.

Every project has its own record, giving you visibility of application progress, DNO references, documents, messages and available approval or commissioning information.

  • Current project status
  • DNO application reference
  • Project documentation
  • Comments and questions
  • Application history
  • Important updates and milestones

Questions about a live project?

Use Comments & Questions on the project page to contact our team and keep the conversation attached to the application.

Illustrative project preview

DNO-247831

14 Ashfield Rd, LS8 4EW

With DNO Engineer
Current status
DNO reference
Documents
Comments & questions
Submitted to DNO2 days ago
Documents uploaded3 days ago
Project created5 days ago

DNO timescales

Assessment times vary.

DNO assessment times depend on the network operator, application type, project size, technical complexity and whether additional studies or reinforcement are required. We'll explain the relevant guidance and keep you informed as the application progresses.

View DNO Timescale Guidance

Fees & DNO charges

Our fee and DNO charges are separate.

You pay DNO Renewables for the service we provide. Depending on the project, the network operator may charge separately for application assessment, design, studies, connection works or other network activities.

We don't control DNO charges. Where the network operator advises us of a charge, we'll pass the information to you before progressing where a decision or payment is required.

View Our Pricing
Why DNO Renewables

One specialist team. Clear communication throughout.

Whether we're managing a single application or supporting an ongoing programme, our focus is on keeping the DNO process organised, transparent and moving forward.

Specialist Review

Applications are reviewed before submission to identify missing or inconsistent information.

Proactive Chasing

We follow up with the DNO and pursue outstanding responses throughout the application.

One Project Record

Documents, correspondence and application milestones are kept together in your portal.

UK-Wide Support

Our UK-based team manages applications across every UK distribution network operator.

Ready when you are

Not sure which stage you're at?

Tell us a little about your project and we'll help identify the right starting point, whether that's feasibility, a formal application or ongoing DNO management.

  • Every UK DNO
  • Domestic to Utility-Scale
  • UK-Based Team
Find What I Need
Not sure which service you need? Find your route

Prepared, submitted and chased by our UK team. You track it in the portal.

Common questions

Frequently asked questions