DNO ApplicationsG99Installers5 min read

Who Can Submit a G99 Application? A UK Guide for Installers and Site Owners

The short answer, who is responsible, and the documents you need for the DNO to accept a G99 application first time.

By DNO Renewables Editorial · Published

The short answer

A G99 application can be submitted by the installer, a specialist application service working on the installer's behalf, an electrical consultant, or the site owner. The Distribution Network Operator (DNO) assesses the application and decides whether, and on what terms, the system can connect.

For most solar PV, battery and EV projects, the installer or their outsourced application partner submits it. Not sure whether your project needs G99 or G98? Read our G99 vs G98 guide.

Who can submit, and when each option makes sense

  • The installer: the usual route for domestic and small commercial systems. They know the equipment, design and site.
  • An outsourced G99 specialist: for installers who don't want G99 paperwork tying up their team, or who send a high volume of applications. The specialist prepares the pack, submits it, answers DNO queries and handles commissioning forms.
  • An electrical or grid consultant: for larger commercial, export-limited or high-voltage projects that need studies or protection design.
  • The site owner: possible, but rarely practical without the technical data the installer holds.

What a G99 application needs

  • Site address, postcode and MPAN
  • Customer details and a signed letter of authority
  • Inverter make, model and type-test (ENA) reference
  • Battery, EV charger or heat pump details where relevant
  • Total generation capacity and requested export capacity
  • Single line diagram (SLD) showing protection and isolation
  • Cut-out rating and supply phase
  • Export limitation scheme details if export is restricted

Incomplete packs are a leading cause of DNO queries and delays. See why DNO applications get rejected.

What happens after submission

The DNO checks the application, may ask technical questions, and then approves it, approves it with an export limit, or issues a connection offer if network works are needed. Once the system is installed, commissioning paperwork goes back to the DNO to complete the process. Timescales vary by DNO and project, so it pays to submit early.

Frequently asked questions

Can a homeowner submit their own G99 application?

Yes, anyone can apply to the DNO, but most homeowners rely on their installer. The application needs inverter type-test data, protection settings and a single line diagram, which the installer holds.

Does an MCS installer have to submit the G99 application?

Under MCS requirements the installer is responsible for making sure the DNO application or notification is made for the system they install. Many installers outsource the paperwork while keeping that responsibility.

Can I outsource G99 applications as an installer?

Yes. A specialist can prepare the forms, single line diagram and supporting documents, submit them to the DNO, answer technical queries and handle commissioning paperwork, all in your name or your customer's.

Do I need G99 approval before installing?

Yes. G99 systems need DNO approval before they are connected. G98 systems up to 16A per phase can usually be installed first and notified within 28 days.

How much does it cost to have a G99 application submitted for you?

DNO Renewables prepares and submits G99 applications from £125 + VAT for systems up to 50kW. Any network operator charges are separate and set by the DNO.

Let us handle your grid connection work

DNO applications, feasibility, site surveys and new connections. We submit, track, and manage so you can focus on installing.

View Pricing