Solar & BatteryGrid ConnectionsUtility-scale6 min read

10MW, 20MW and 50MW+ Solar Farm and BESS Grid Connections: A UK Guide

What changes as solar and battery projects grow from 1MW to 50MW+, and how to get yours to a connection offer you can build.

By DNO Renewables Editorial · Published

How project size changes the connection

  • 1–10MW: C&I rooftops and smaller ground-mount sites, usually connected at 11kV, often with export limitation.
  • 10–20MW: solar farms and co-located BESS, typically at 33kV, with a shared connection for hybrids.
  • 20–50MW: utility solar and standalone BESS. Queue position, reinforcement and flexible connection terms shape whether the project is viable.
  • 50MW+: EHV and 132kV connections, where the transmission network and NESO come into play.

Battery storage: import matters as much as export

A BESS needs import capacity to charge as well as export capacity to discharge. Setting the two separately, and taking up a curtailable or flexible connection where the DNO offers one, can turn a stalled project into a viable one. Hybrid solar + BESS sites can often share one export capacity, for example 30MW PV with 20MW / 40MWh storage.

Queue reform and Gate 2

Connections reform has moved the queue from first come, first served to first ready, first connected. To secure a firm position, projects need evidence of land rights and planning progress, plus a realistic delivery programme. Get the groundwork done before you apply.

Who builds the connection

The non-contestable works stay with the DNO, but much of a large connection can be built by an accredited ICP. We compare the two routes in DNO or ICP? Understanding your grid connection delivery options.

Frequently asked questions

What voltage does a 20MW solar farm connect at?

Usually 33kV, although it depends on local network capacity. Smaller schemes up to around 10MW often connect at 11kV, and projects of 50MW+ commonly need 132kV.

How long does a 50MW BESS grid connection take?

The DNO has a set period to issue an offer once the application is complete, but the connection date in that offer can be years away, depending on reinforcement and transmission works. Under queue reform, projects that are ready to proceed get priority.

Do I need a transmission impact assessment?

Larger distribution-connected projects can affect the transmission network, and the DNO may refer them to NESO. That adds time and can bring extra works or securities.

Can an ICP build my connection?

Yes. The contestable parts of the works can be built by an accredited ICP, which on large projects can improve both programme and cost.