1. Site and supply details
The DNO needs to know exactly where the system connects and what the existing supply can handle. Check these on site rather than relying on a customer's description.
- Full site address and postcode
- MPAN (or confirmation that the site is a new build with no supply yet)
- Supply phase: single phase or three phase
- Cut-out (main fuse) rating, ideally with a clear photo
- Any existing generation already on the site, such as older solar PV
Not sure which network operator covers the site? Use our DNO postcode finder.
2. Equipment details
The DNO assesses the total capacity connecting to its network, so every piece of generating or storage equipment needs to be listed, not just the main inverter.
- Inverter make, model, rating and quantity
- ENA type-test reference for each inverter
- Solar panel make, model, wattage and number of panels
- Battery make, model, capacity and whether it can export
- EV chargers and heat pumps being installed at the same time
- Total generation capacity and the export capacity you are requesting
If the system exceeds the supply or the DNO's limits, an export limitation scheme may be needed. Include its details up front rather than waiting to be asked.
3. Supporting documents
- Signed letter of authority (LOA) from the customer
- Single line diagram (SLD) showing protection and isolation
- Inverter and battery datasheets
- Export limitation details, if export is restricted
- Any existing DNO approval for equipment already on site
The LOA is the most common hold-up. Without it the DNO cannot act on the customer's behalf, so get it signed at the point of sale. For more common pitfalls, read why DNO applications get rejected.
4. Installer and customer details
- Installer company name, contact name, phone and email
- MCS certification number, where relevant
- Customer name, phone and email
- Planned installation date
Send us what you have and our UK team prepares the forms, produces the SLD where needed, submits to the DNO and manages it through to a decision.
We prepare, submit and chase G99 applications with every UK DNO, from £125 + VAT.
See G99 pricingWe handle DNO correspondence, technical queries and progress chasing after submission.
How we manage itCheck which network operator covers your site by postcode.
Search by postcodeWhat happens after you submit
The DNO checks the application and may raise technical queries. It then approves the application, approves it with an export limit, or issues a connection offer if network work is needed. Timescales vary by DNO and by project, and the DNO controls its own decision and timetable.
Once the system is installed, commissioning paperwork goes back to the DNO to close the application. Unsure whether you need G99 at all? See our G99 vs G98 guide.
Frequently asked questions
What is the most common reason a G99 application is held up?
Missing or incomplete documents. A missing letter of authority, an out-of-date single line diagram or an inverter without a matching ENA type-test reference will usually trigger a DNO query before the application can progress.
Do I need the MPAN to submit a G99 application?
In most cases, yes. The MPAN identifies the supply point. If the site is a new build without a supply, or the MPAN can't be found, this needs to be flagged so the DNO can treat the application correctly.
Does a battery need to be included on a G99 application?
Yes. Batteries count towards the generation capacity the DNO assesses, so make, model, rating and whether the battery can export to the grid should all be included.
Can I start installing before G99 approval?
No. G99 systems need DNO approval before they are connected. Installing first risks having to change the design if the DNO applies an export limit or other conditions.
Does your £125 fee include DNO charges?
No. Our fee covers preparing, submitting and managing the application. Any fees the DNO charges are separate and set by the network operator.
Where this fits in your journey
Stage 03 of 5 · Formal Application
Submit to the DNO
Let us handle your grid connection work
DNO applications, feasibility, site surveys and new connections. We submit, track, and manage so you can focus on installing.