DNO Fees Explained: What Network Operators Charge and Why

The four types of DNO charge, what pushes them up, and how to quote your customers without nasty surprises.

By DNO Renewables Editorial · Published

Why DNOs charge fees

Distribution Network Operators (DNOs) are responsible for keeping the local electricity network safe and stable. When a new system connects, they may need to assess its impact, run network studies or carry out physical work. Those costs are recovered through charges set out in each DNO's charging statement.

For a typical domestic system, the DNO often only needs to check the application, and there may be no charge. Larger and more complex projects take more engineering time, and the charges reflect that.

The four types of DNO charge

Up front
Application / assessment fee

Charged by some DNOs to assess larger or more complex applications. Many small domestic G98 and G99 applications carry no assessment fee.

With the offer
Connection offer charges

If the DNO needs to do work to connect the system, the connection offer sets out the cost and the terms for that work.

Network work
Reinforcement costs

Where the local network can't take the extra capacity, upgrades may be needed. Part of this cost can be passed to the customer.

After submission
Modification / variation fees

Changing capacity, equipment or design after an application or offer is issued can lead to a re-assessment and a further charge.

Why fees differ between DNOs

There are six main DNO groups in Great Britain, plus independent network operators (IDNOs). Each publishes its own charging methodology, so there is no single national price list. Two identical systems in different regions can receive very different quotes, depending on the local network and the work needed.

Some operators also split charges into bands by voltage level or connection type, so a system being assessed in the wrong band can show an unexpected cost. If a figure looks wrong, it is worth querying before the customer accepts it. Find your operator on our DNO applications hub.

What drives fees up

Common cost drivers
  • Larger generation or export capacity
  • Three-phase and commercial connections
  • Constrained local networks that need reinforcement
  • Export limitation studies or protection requirements
  • Changes to the design after submission

How to budget as an installer

  • Quote DNO charges separately. Keep them apart from your installation price so customers understand who sets them.
  • Flag the risk early. For larger or three-phase systems, tell customers at the quote stage that DNO charges may apply.
  • Check feasibility on bigger projects. A feasibility study gives indicative capacity, constraints and costs before design is fixed.
  • Get offers reviewed. A connection offer review can show whether a design change could lower the cost.

Our fee vs DNO fees

Our G99 application service starts at £125 + VAT and covers preparing the forms and documents, submitting to the DNO and managing the application through to a decision. It does not include any charges the DNO makes. Those are set by the network operator and paid separately.

Frequently asked questions

Do all DNO applications have a fee?

No. Many small domestic applications have no DNO charge. Fees are more likely for larger systems, three-phase or commercial connections, and projects that need network studies or work.

Who pays the DNO fee?

The applicant, usually passed on to the end customer. It should be shown separately from the installation price and from any application service fee.

Does your £125 fee include DNO charges?

No. Our fee covers preparing, submitting and managing the application. Any fees the DNO charges are separate and set by the network operator.

Why is one DNO more expensive than another?

Each DNO sets its own charging methodology, and costs depend on the local network, the voltage level and the work required. The same system can cost different amounts in different regions.

Can DNO fees be reduced?

Sometimes. Reducing the requested export capacity, adding export limitation or adjusting the design can lower or avoid network work. A connection offer review can show which options are realistic.

Where this fits in your journey

Stage 03 of 5 · Formal Application

Submit to the DNO

Let us handle your grid connection work

DNO applications, feasibility, site surveys and new connections. We submit, track, and manage so you can focus on installing.

View Pricing